Every E-House MCT system we crate in Shaanxi raises one question: how many spare sealing modules and compression units go in IP68 ingress protection 1? Too few stalls commissioning; too many wastes budget.
Ship spare sealing modules and compression units for an E-House MCT system based on three variables: at least 20% spare frame capacity, the count of unused openings, and one spare compression wedge plus stayplate set per five frames, adjusted for EMC or Ex duty.
That answer is short. The reasoning behind it is not. Below I walk through the ratio math, the 20% rule, the two ways buyers get the count wrong, and how a free sample fit test locks the number down before you sign a bulk order.
How do I calculate the right ratio of spare sealing modules to compression units for my E-House frame count?
Last quarter our QC team in Shandong pulled a packed E-House crate because the spare-module tally did not match the frame count on the drawing IATF 16949 2. That check caught a gap.
Calculate the ratio per frame: one compression wedge and one stayplate set per frame installed, plus one spare wedge and stayplate set per five frames. Then add sealing modules until 20% of each frame's packing space is filled with spare blocks.

The ratio is not a single number for the whole project. It is built frame by frame. Multi-cable transit frames come in different heights and widths, so a 2×2 frame and a 6×1 frame need very different spare counts even on the same E-House wall. I always start from the frame schedule, not from the cable list.
Start with the packing space calculation
The frame drawing gives me the total block area. From there I work through four steps.
- Count the cables per frame and record each cable's outer diameter.
- Assign each service two insert blocks. This is the normal packing method for a single cable within a row.
- Sum the area of the installed blocks and subtract it from the frame's total block area. The remainder is your unused rubber space.
- Fill that remainder with solid spare blocks or blank modules. If the remainder is under 20% of total area, add frame height or add another frame.
Stayplates sit between rows and carry the load from the compression wedge into the blocks. Every frame needs its full set. Compression wedges then apply uniform force across every row. Without both parts, the gas-tight sealing rating of the transit cannot be reached, no matter how many rubber modules you ship. So the compression hardware is part of the seal, not an accessory.
Ratio table by frame count
| Installed frames | Wedge + stayplate sets installed | Spare wedge + stayplate sets (1 per 5) | Offshore or high-vibration (+10%, rounded up) | Spare block area target |
|---|---|---|---|---|
| 5 | 5 | 1 | 2 | ≥20% of each frame |
| 10 | 10 | 2 | 3 | ≥20% of each frame |
| 20 | 20 | 4 | 5 | ≥20% of each frame |
| 40 | 40 | 8 | 9 | ≥20% of each frame |
The 10% uplift for offshore platforms and high-vibration sites covers mechanical settling during transport. A wedge that was torqued in our factory can loosen slightly after a long sea voyage, and the installer may need a fresh one at commissioning.
One more practical note. Our TSC square modules and TSR round cable penetration seals are dimensionally compatible with common 120-frame standards. That means the ratio math above works with the same frame geometry your incumbent supplier uses. You do not need to recalculate frame area when you qualify us as a second source.
What percentage of extra sealing modules should I stock for future cable additions in my E-House project?
On each BESS or modular substation order we weigh the same trade-off: more spare rubber protects tomorrow's cable pull, but adds crate weight and cost today.
Stock a minimum of 20% extra sealing modules, measured as unused block area against total block area per frame. Increase that figure when the client's expansion plan reserves additional circuits, and supply spares in a size mix that mirrors the cable schedule.

The 20% figure is the most quoted number in this topic, and it is often misread. It is not "ship 20% more pieces." It is a rule about area. The industry reference states that spare capacity should equal at least 20% of the total block area, calculated from the unused rubber blocks in the frame. That distinction changes how you write the BOM.
Why the area rule matters more than a piece count
An MCT frame must be completely filled before compression. Any empty gap breaks the seal path. Fire-rated cable transits rated A-0 or A-60, and transits rated IP68, only meet those ratings when every row is packed and compressed. So the "full-frame" rule and the 20% rule work together. First you fill the frame with installed modules plus spare blocks. Then you confirm that the spare blocks alone make up at least one fifth of the area. If they do not, the frame is too small for the future the client has planned.
In modular substation design 3, the expansion plan is usually written down. I ask for it. If the electrical package reserves six future feeders through one wall, I size the spare block area to accept six cables of the listed diameters, even if that pushes the frame above 20%. The spec beats the rule of thumb.
Fixed-size versus step-core spares
| Spare strategy | What you stock | Onsite flexibility | Storage burden |
|---|---|---|---|
| Fixed-size modules | Several module sizes matching each cable OD on the schedule | Low. A cable upsized in the field needs a different part number | High. Multiple SKUs per frame type |
| Step-core multidiameter modules | One or two module sizes covering a wide cable diameter range | High. Peel the core to the cable OD on site | Low. Fewer SKUs, fewer partial boxes |
Our TSC modules use step-core, halogen-free EPDM rubber. One module size adapts to a range of cable diameters. That is why some engineers now specify multidiameter modules for the entire spare inventory. It removes the guesswork about which fixed size will be needed in year ten.
Two further points shape the percentage. First, EMC, EMP, ESD, or Ex-rated transits may use different modules or top sealing pieces than a standard transit. The spare mix must match the compliance class of each frame, or the spare is useless when you need it. Second, spares must survive storage. We pack spare elastomer in UV-protected packaging and advise climate-controlled storage, because hardened rubber will not compress correctly after years on a shelf across a 25-year E-House lifecycle.
How do I avoid over-ordering or under-ordering spare MCT parts when specifying my E-House system?
A sourcing engineer in Germany once sent us two competing BOMs for the same E-House. One over-ordered spares by a full crate; the other left out stayplates entirely.
Avoid both errors by splitting spares into two lists: a commissioning kit sized for installation damage and field upsizing, and an operational stock set by the specification's spare capacity requirements. Then verify compression wedges, stayplates, and top pieces against each frame drawing before release.

Both BOMs in that story came from a reasonable idea taken too far. I hear three procurement stances on almost every E-House project. Each one has a valid point and a blind spot.
Three procurement stances and where each one breaks
| Stance | What the buyer argues | Where it breaks | How I resolve it |
|---|---|---|---|
| Conservative | Ship generous spares to protect uptime on a mission-critical E-House | Cost, crate weight, and rubber that may never be installed | Cap spares at the area rule plus a defined commissioning kit; do not pad both |
| Lean logistics | Ship only what the spec demands to cut cost and storage | A damaged module or a missing wedge stops commissioning on site | Keep operational spares lean, but never cut the commissioning kit |
| Specification-driven | Take quantities only from the design package and client standards | The package often lists installed parts but forgets compression hardware | Cross-check the spec against every frame drawing for wedges, stayplates, and top pieces |
The specification-driven stance is the correct starting point. The design package knows the compliance class, the frame sizes, and the expansion plan. But I have seen many packages that list sealing modules in detail and then simply write "compression unit, 1 per frame" with no spare line at all. That is how the German buyer's second BOM lost its stayplates.
Commissioning spare parts are a separate calculation
Commissioning spares cover the build phase. Operational spares cover the next 25 years. Mixing them is the most common cause of both over- and under-ordering.
- Commissioning kit: replacement modules for blocks nicked during cable pulling, one spare wedge and stayplate set per five frames, MCT lubricant, and a small "emergency repair" set of oversized modules for cables that were upsized in final field wiring without notice.
- Operational stock: the spare blocks already installed in the frame under the 20% area rule, plus a modest reserve of step-core modules in the dominant size.
Because our factory does in-house mold making and holds finished spare sealing modules for fast dispatch, integrators can keep the operational reserve small and reorder against a cross-reference table when a real expansion happens. For long-term tracking, some EPC clients now load the spare list into a digital cable transit management system so shelf-life and location are visible for the whole asset life.
Can free validation samples help me confirm the correct spare quantities before I place a bulk order?
We learned early in our export work that a spare-parts estimate on paper is only a guess until someone presses a real module into a real frame.
Yes. Free validation samples let you fit sealing modules, compression wedges, and stayplates into an existing 120-standard frame cutout, confirm cable diameter range coverage, and measure real packing space. That fit test converts a paper spare estimate into a verified bulk order quantity.

The sample stage is where I see spare counts change most often. Not by a lot, but by enough to matter on a forty-frame E-House. Here is the process we run with European integrators, usually over two to three weeks.
A five-step sample validation process
- Send us your current supplier's model list. We return a cross-reference table mapping each existing module and wedge to the DEWIN equivalent.
- Request samples of the two or three module sizes that dominate your cable schedule, plus one compression wedge and one stayplate set.
- Fit the samples into a spare frame cutout on your own bench or a mock-up wall. Check that the module stack height matches the frame opening within your incumbent's tolerance.
- Peel the step-core to the smallest and largest cable diameters on the schedule. Confirm one module size really covers the cable diameter range you planned for.
- Recount spare block area with the measured stack heights. Adjust the spare module quantity and the spare wedge count, then release the bulk order.
What the sample should prove
| Check | Why it changes the spare count |
|---|---|
| Drop-in fit in a 120-standard frame | Confirms your existing frame area math still applies to the second-source modules |
| Step-core coverage of the schedule | May cut several fixed-size SKUs down to one or two multidiameter sizes |
| Wedge and stayplate interface | Confirms the spare compression hardware works with your installed frames |
| Test documentation | Confirms the ratings you specified are met by the modules you are counting |
Alongside the samples, ask for the evidence. We supply test documents for A-0/A-60 fire rating 4, IP68 ingress protection, and watertight and gas-tight sealing from 0.01 to 0.4 MPa on request, plus CAD and STEP files so your drawing office can model the packed frame before the crate leaves. Our quality systems are certified to ISO 9001 5 and IATF 16949, and the factory is BV-approved. A skeptical purchasing engineer should read those documents before trusting any spare count, including ours. The sample proves the fit. The documents prove the rating. Together they make the bulk quantity defensible in a design review.
Conclusion
Under-shipping spare sealing modules and compression units stalls an E-House MCT system on site; over-shipping wastes budget. The fix: 20% capacity, per-frame wedge ratios, verified samples.
Footnotes
1. The IEC provides the official definitions for IP ratings, including the IP68 standard mentioned. ↩︎
2. IATF 16949 is the global quality management standard for the automotive industry cited for compliance. ↩︎
3. The article discusses spare parts specifically within the context of modular substation projects. ↩︎
4. The IMO sets international standards for fire protection, relevant to A-60 rated cable transits. ↩︎
5. ISO 9001 is the international standard for quality management systems mentioned in the article. ↩︎